PROJECT DETAILS

  • Solutions: Air-conditioning, Ventilation, Heating, Sprinklers
  • Date of implementation: January 2010
  • Location: Krakow, Poland
  • Klient: Nowbud
  • Surface: 6851 m2

ABOUT THE PROJECT

Scope of the project:

– Mechanical ventilation – supply-exhaust air-handling units on the roof with the total capacity of 39,000 m3/h
– Air-conditioning – VRF-GHP system based on gas heat pumps operating with an ecological coolant R410A, VRF-3 pipe system enabling simultaneous heating and cooling in one system – the total cooling power of GHP units installed on the roof: approx. 460 kW
– Sprinklers installation with a pumping station.